In Q1 of 2023 we worked on agreement of a trajectory for storage. We came to a consensus on the separation of storage and commitment. This epic is meant to be the follow up on this ADR.
Work Breakdown
Phase 1
Completion Estimate: 2-3 weeks (23rd August)
The content you are editing has changed. Please copy your edits and refresh the page.
Summary
In Q1 of 2023 we worked on agreement of a trajectory for storage. We came to a consensus on the separation of storage and commitment. This epic is meant to be the follow up on this ADR.
Work Breakdown
Phase 1
Completion Estimate: 2-3 weeks (23rd August)
Tasks for SS
Tasks for SC
Phase 2
Completion Estimate: TBD
Tasks
internal
module fromstore
#18738Phase 3
Completion Estimate: TBD
Tasks
The text was updated successfully, but these errors were encountered: