PMBOK p.257
Project documents:
EEF Enterprise Environmental Factors OPA Organizational process assets
Expert judgement - see dd Stakeholder register Data analysis:
- Earned value analysis
- Variance analysis
- Trend analysis
- Reserve analysis
To-complete performance index
Project management information system
new Work perfomance information new dd Cost forecasts new dd Change requests
Project management plan updates: root Project management plan
- updates to qq Cost management plan
- updates to qq Cost baseline
- updates to Performance measurement baseline
Project document updates:
- updates to dd Assumption log
- updates to dd Basis of estimates
- updates to dd Cost estimates
- updates to dd Lessons learned register
- updates to dd Risk register